<?xml version="1.0" encoding="utf-8"?><feed xmlns="http://www.w3.org/2005/Atom" ><generator uri="https://jekyllrb.com/" version="3.9.0">Jekyll</generator><link href="https://mardh.eu/feed.xml" rel="self" type="application/atom+xml" /><link href="https://mardh.eu/" rel="alternate" type="text/html" /><updated>2021-10-06T05:49:45+00:00</updated><id>https://mardh.eu/feed.xml</id><title type="html">Tom and the Oak</title><subtitle>Insights from an Agile Coach who is passionate about  finding sustainable solutions that provide lasting  improvements for both individual and organization.</subtitle><entry><title type="html">Committed People or Committed Scope?</title><link href="https://mardh.eu/post/2021/10/05/committed-people-or-committed-scope.html" rel="alternate" type="text/html" title="Committed People or Committed Scope?" /><published>2021-10-05T06:00:49+00:00</published><updated>2021-10-05T06:00:49+00:00</updated><id>https://mardh.eu/post/2021/10/05/committed-people-or-committed-scope</id><content type="html" xml:base="https://mardh.eu/post/2021/10/05/committed-people-or-committed-scope.html">&lt;p&gt;&lt;img src=&quot;../../../../assets/posts/committed-people.jpg&quot; alt=&quot;story point estimation&quot; /&gt;&lt;/p&gt;

&lt;p&gt;The question, “What have you committed to?”, gives many different associations. In my world as an Agile Coach I have reflected quite a lot about this in terms of the result of a planing session. What is the scope that we can commit to? For me the association to the word commitment is more of a burden than something that gives me a lot of energy. One voice raised from a team member in one team was&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;Commit, it is something that we have promised to deliver and we need to be ashamed if we cannot&lt;/p&gt;
&lt;/blockquote&gt;

&lt;p&gt;Another answer to what association comes from commitment&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;Commitment, is for me a word that is connected with to be engaged and determined about something&lt;/p&gt;
&lt;/blockquote&gt;

&lt;p&gt;Yeah, that is of course also a correct aspect of commitment, that I did not think of at first. Probably this is the most common association for those not being that deeply involved in software development and having to argue why we could not deliver. You had committed to it, right?&lt;/p&gt;

&lt;h2 id=&quot;committed-people&quot;&gt;Committed people&lt;/h2&gt;

&lt;p&gt;Committed people spread a lot of joy and generates a lot of energy. Their conviction and determination is something really powerful and that is something we are striving for. It increases the motivation both for those that have a true commitment and for those that collaborates with them.&lt;/p&gt;

&lt;p&gt;Looking back at previous versions of the Scrum Guide&lt;sup id=&quot;fnref:1&quot; role=&quot;doc-noteref&quot;&gt;&lt;a href=&quot;#fn:1&quot; class=&quot;footnote&quot; rel=&quot;footnote&quot;&gt;1&lt;/a&gt;&lt;/sup&gt;, the planned scope was something the team commits to. That description was abandoned since it resulted in bad behavior. Now the term commitment is back again, but in the meaning that people show commitment to&lt;/p&gt;

&lt;ul&gt;
  &lt;li&gt;Product Goal&lt;/li&gt;
  &lt;li&gt;Sprint Goal&lt;/li&gt;
  &lt;li&gt;Definition of Done&lt;/li&gt;
&lt;/ul&gt;

&lt;h2 id=&quot;expected-scope&quot;&gt;Expected Scope&lt;/h2&gt;

&lt;p&gt;SAFe&lt;sup id=&quot;fnref:2&quot; role=&quot;doc-noteref&quot;&gt;&lt;a href=&quot;#fn:2&quot; class=&quot;footnote&quot; rel=&quot;footnote&quot;&gt;2&lt;/a&gt;&lt;/sup&gt; still holds on to this definition of commitment:&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;SAFe commitment has two parts:&lt;/p&gt;
  &lt;ul&gt;
    &lt;li&gt;Teams agree to do everything reasonably in their power to meet the committed objectives&lt;/li&gt;
    &lt;li&gt;During the course of the PI, if it’s discovered that some objectives are not achievable, then the teams agree to escalate immediately so that stakeholders are informed and corrective action can be taken&lt;/li&gt;
  &lt;/ul&gt;

  &lt;p&gt;© Scaled Agile, Inc.&lt;/p&gt;
&lt;/blockquote&gt;

&lt;p&gt;Why should we not act the same way for the uncommitted objectives?&lt;/p&gt;

&lt;p&gt;Is there an alternative way to talk about this when it comes to parts of a plan or a forecast?&lt;/p&gt;

&lt;p&gt;Yes, there is. The stakeholders will always want to know what they can expect after a planning session like sprint planning or PI Planning. The main problem is that we do not really know since we most of the time operate in a complex environment. I would suggest that we talk about expected items that the stakeholder can expect from us and other items that are uncertain. Not uncertain because of capacity issues, but because they are related to a risk that affects how likely it is that we really can deliver. If the risk is to high the item is uncertain.&lt;/p&gt;

&lt;p&gt;The same person that i quoted in the beginning of this article also gave this reflection about a forecast&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;Forecast, it does not mean that we promise to deliver, but we will do our very best. The forecast is the best picture of what we think we can accomplish&lt;/p&gt;
&lt;/blockquote&gt;

&lt;h2 id=&quot;summary&quot;&gt;Summary&lt;/h2&gt;

&lt;p&gt;We all want committed people around us, because that motivates us. Committed scope is something that can decrease our motivation and I hope that using the word commitment for scope is something that we could move away from. Instead use words like &lt;strong&gt;&lt;a href=&quot;/terms/expected.html&quot;&gt;expected items&lt;/a&gt;&lt;/strong&gt; for the scope that is planned for and that a stakeholder can expect to get and &lt;strong&gt;&lt;a href=&quot;/terms/uncertain.html&quot;&gt;uncertain items&lt;/a&gt;&lt;/strong&gt; for scope connected to a risk.&lt;/p&gt;

&lt;hr /&gt;

&lt;div class=&quot;footnotes&quot; role=&quot;doc-endnotes&quot;&gt;
  &lt;ol&gt;
    &lt;li id=&quot;fn:1&quot; role=&quot;doc-endnote&quot;&gt;
      &lt;p&gt;&lt;a href=&quot;https://scrumguides.org/docs/scrumguide/v2020/2020-Scrum-Guide-US.pdf&quot;&gt;The Scrum Guide (November 2020)&lt;/a&gt; &lt;a href=&quot;#fnref:1&quot; class=&quot;reversefootnote&quot; role=&quot;doc-backlink&quot;&gt;&amp;#8617;&lt;/a&gt;&lt;/p&gt;
    &lt;/li&gt;
    &lt;li id=&quot;fn:2&quot; role=&quot;doc-endnote&quot;&gt;
      &lt;p&gt;&lt;a href=&quot;https://www.scaledagileframework.com/pi-objectives/&quot;&gt;SAFe - about PI Objectives (2021-10-05)&lt;/a&gt; &lt;a href=&quot;#fnref:2&quot; class=&quot;reversefootnote&quot; role=&quot;doc-backlink&quot;&gt;&amp;#8617;&lt;/a&gt;&lt;/p&gt;
    &lt;/li&gt;
  &lt;/ol&gt;
&lt;/div&gt;</content><author><name></name></author><category term="post" /><summary type="html"></summary><media:thumbnail xmlns:media="http://search.yahoo.com/mrss/" url="https://mardh.eu/assets/posts/committed-people.jpg" /><media:content medium="image" url="https://mardh.eu/assets/posts/committed-people.jpg" xmlns:media="http://search.yahoo.com/mrss/" /></entry><entry><title type="html">Three things you do not have to consider using story point estimation</title><link href="https://mardh.eu/post/2021/08/26/three-things-about-story-point-estimation.html" rel="alternate" type="text/html" title="Three things you do not have to consider using story point estimation" /><published>2021-08-26T18:20:49+00:00</published><updated>2021-08-26T18:20:49+00:00</updated><id>https://mardh.eu/post/2021/08/26/three-things-about-story-point-estimation</id><content type="html" xml:base="https://mardh.eu/post/2021/08/26/three-things-about-story-point-estimation.html">&lt;p&gt;&lt;img src=&quot;../../../../assets/posts/storypointestimation.jpg&quot; alt=&quot;story point estimation&quot; /&gt;&lt;/p&gt;

&lt;ul&gt;
  &lt;li&gt;How much work is remaining and how long time it will take&lt;/li&gt;
  &lt;li&gt;Resource planning to make sure everyone in the team are occupied&lt;/li&gt;
  &lt;li&gt;Common understanding of what the story is all about&lt;/li&gt;
&lt;/ul&gt;

&lt;p&gt;During a discussion around planning in a software development team we come to talk about how hard it is to estimate how many story points that remains on the stories that will spillover to the next sprint. This is a common misunderstanding of how story points should be used.&lt;/p&gt;

&lt;h2 id=&quot;capacity-of-future-sprints&quot;&gt;Capacity of future sprints&lt;/h2&gt;

&lt;p&gt;One of the reasons why teams pick up story point estimation is because they would like to understand their capacity in terms of how many of the stories fits in a sprint considering the size of them in story points. To make story points useful for this we need to work with them in a good and structured way. Stories are refined and estimated using story points and the story point estimation is a whole team exercise. It is normally performed using planning poker&lt;sup id=&quot;fnref:1&quot; role=&quot;doc-noteref&quot;&gt;&lt;a href=&quot;#fn:1&quot; class=&quot;footnote&quot; rel=&quot;footnote&quot;&gt;1&lt;/a&gt;&lt;/sup&gt;. The estimate that a story gets should not be changed and when a story is done all story points of that story is added to that sprints velocity.&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;When a sprint ends and a story is not done, zero points are are accounted for and the whole story goes into the next sprint along with all its story points (if it is still prioritized in the sprint planning).&lt;/p&gt;
&lt;/blockquote&gt;

&lt;p&gt;It is not possible to know how much of the story, or complexity of the story, that were completed last sprint and how much that remains for the coming sprint. Looking back at the velocity of the completed sprints we get an idea of what the capacity of the team is. This is not a pure mathematical exercise.&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;The capacity for the coming iteration can be made based upon the velocity of the recently closed iterations together with a judgment from the team. Is there is anything else that affects the team capacity?&lt;/p&gt;
&lt;/blockquote&gt;

&lt;h2 id=&quot;how-do-all-the-other-work-affect-the-capacity&quot;&gt;How do all the other work affect the capacity?&lt;/h2&gt;

&lt;p&gt;The stories that we are estimated assumes to be created to deliver some kind of value to the customers. This is not the only thing that is worked upon during a sprint. I will touch upon a few different kind of work types and explain why they should not be stories and how that is managed from a capacity point of view.&lt;/p&gt;

&lt;p&gt;Bugs, it could be hard to know how many bugs that will be reported the coming sprint, but the best assumption is that it will be roughly as many as in the previous sprint. The same reasoning goes for for example support and line meetings. There is no major differences between the situation in the previous vs future sprints that might affect capacity, i.e. how many story points of stories that is the capacity going forward.&lt;/p&gt;

&lt;table&gt;
  &lt;thead&gt;
    &lt;tr&gt;
      &lt;th style=&quot;text-align: left&quot;&gt;Previous sprint&lt;/th&gt;
      &lt;th style=&quot;text-align: left&quot;&gt;Current sprint&lt;/th&gt;
      &lt;th style=&quot;text-align: left&quot;&gt;Next Sprint&lt;/th&gt;
    &lt;/tr&gt;
  &lt;/thead&gt;
  &lt;tbody&gt;
    &lt;tr&gt;
      &lt;td style=&quot;text-align: left&quot;&gt;Refinement work&lt;/td&gt;
      &lt;td style=&quot;text-align: left&quot;&gt;Development and test&lt;/td&gt;
      &lt;td style=&quot;text-align: left&quot;&gt;Support and bugs&lt;/td&gt;
    &lt;/tr&gt;
  &lt;/tbody&gt;
&lt;/table&gt;

&lt;p&gt;Use only story point for the work from definition of ready (DoR) and definition of done (DoD). Refinement work is done when DoR is fulfilled and DoD should describe when a story is done, still we need to support and fix bugs after DoD. These different work types exists in all sprints with a similar distribution and that is why it is built in to the system and we only need to estimate stories.&lt;/p&gt;

&lt;h2 id=&quot;the-main-benefit-of-story-point-estimation&quot;&gt;The main benefit of story point estimation&lt;/h2&gt;

&lt;p&gt;Some teams abandons story point estimation and scrum since they feel it takes unnecessary time and effort. Instead they use kanban to manage the flow of stories. It might be the right thing to do. It depends… When I ask teams about how they gain and share understanding of the stories after this change they normally do not understand why I ask the question.&lt;/p&gt;

&lt;blockquote&gt;
  &lt;p&gt;Story point estimation done with planning poker not only gets us the estimates but also an increased understanding of what the stories are all about&lt;/p&gt;
&lt;/blockquote&gt;

&lt;p&gt;This is far more important than the estimated story points.&lt;/p&gt;

&lt;h2 id=&quot;summary&quot;&gt;Summary&lt;/h2&gt;
&lt;p&gt;All in all there is a lot of value in doing story point estimation with planning poker with the entire team. Done right it will give us&lt;/p&gt;

&lt;ul&gt;
  &lt;li&gt;increased understanding of what the story is all about&lt;/li&gt;
  &lt;li&gt;velocity from previous sprints to use when establishing capacity for coming sprints&lt;/li&gt;
  &lt;li&gt;Less focus on time and how to keep everyone busy&lt;/li&gt;
&lt;/ul&gt;

&lt;hr /&gt;

&lt;div class=&quot;footnotes&quot; role=&quot;doc-endnotes&quot;&gt;
  &lt;ol&gt;
    &lt;li id=&quot;fn:1&quot; role=&quot;doc-endnote&quot;&gt;
      &lt;p&gt;&lt;a href=&quot;https://en.wikipedia.org/wiki/Planning_poker&quot;&gt;Wikipedia: Planning Poker&lt;/a&gt; &lt;a href=&quot;#fnref:1&quot; class=&quot;reversefootnote&quot; role=&quot;doc-backlink&quot;&gt;&amp;#8617;&lt;/a&gt;&lt;/p&gt;
    &lt;/li&gt;
  &lt;/ol&gt;
&lt;/div&gt;</content><author><name></name></author><category term="post" /><summary type="html"></summary><media:thumbnail xmlns:media="http://search.yahoo.com/mrss/" url="https://mardh.eu/assets/posts/storypointestimation.jpg" /><media:content medium="image" url="https://mardh.eu/assets/posts/storypointestimation.jpg" xmlns:media="http://search.yahoo.com/mrss/" /></entry></feed>